Rebuilding Wellington's central library could cost $67m less than earthquake-strengthening

Friday, 22 May 2020

It will cost almost $200 million to strengthen Wellington
It will cost almost $200 million to strengthen Wellington's earthquake-prone central library. (File photo)

It will cost almost $200 million to earthquake-strengthen Wellington's central library, up to $67m more than building a new library from scratch.

Wellington City Council released details of an engineers' report into the earthquake-prone building on Friday, revealing a range of options for restoring the central city facility which closed in March last year.

The library has been closed since March 2019, with its future up in the air since. (File photo)
The library has been closed since March 2019, with its future up in the air since. (File photo)

Among them are three strengthening options ranging from $90.8m to $199.8m.

The latter would involve a full building services upgrade including base isolators, internal reconfiguration, and better connection to the Civic Square Precinct.

**READ MORE:

* One year since Wellington's library closed, there's no decision on its future

It would cost up to $160 million to demolish the existing library and build a new one. (File photo)
It would cost up to $160 million to demolish the existing library and build a new one. (File photo)

* New Wellington mayor Andy Foster resolute the Central Library should be repaired

Rebuilding a library of the same size would cost about $133m. (File photo)
Rebuilding a library of the same size would cost about $133m. (File photo)

* $23.9m paper deficit on Wellington city council's books after $50.9m write-down of civic assets

* City with a broken heart: Civic Square key focal point for election issues in CEO pre-election report

**

Construction would begin about mid-2022 with the building to open around February 2026.

City councillor Fleur Fitzsimons says the library is no longer a 21st century facility. (File photo)
City councillor Fleur Fitzsimons says the library is no longer a 21st century facility. (File photo)

A 'mid-range' strengthening option was also provided, with a projected cost of $151.8m.

But the report also revealed that demolishing the existing library and constructing a new one of the same size would cost just $133m - $67m cheaper than a potential redevelopment.

Constructing a new library using the whole building in which it is situated - including the third and fourth floors which are currently occupied by office space - would cost $160m.

The library is part of Wellington
The library is part of Wellington's Civic Square precinct. (File photo)

No time frame was given in the report for new builds, but Wellington Mayor Andy Foster said during an online media briefing it would take about one or two years longer than a redevelopment.

When asked if he had a preference, Foster said he was looking forward to hearing the views of Wellingtonians.

However, council officers had 'clearly given us advice we need to go with a high-resilience option'.

The project would be funded through borrowing, adding to the council's cost pressures in the wake of the coronavirus pandemic.

'This is a major decision,' Foster said.

'All of the options are very costly. They are basically 'large' and 'larger'.'

However, the building would have a very long lifespan and the cost would be paid back over a long period of time.

In a statement, Foster said the council wanted a resilient, modern and exciting library.

“This is a huge opportunity to move our central library services from the 1980s into the future.

'Many of us have seen how modern libraries like Christchurch’s Tūranga and our own Waitohi Library in Johnsonville are engaging and connecting people to both the collections, and learning in new ways.

City councillor Fleur Fitzsimons, who holds the council's libraries portfolio, said the current building was no longer suitable as a 21st century library.

“The central library is a precious public space where everyone is welcome. Residents are really missing it, we need to get is open as soon as possible.'

The proposals will be considered by councillors on Wednesday before going out for public feedback in June.

WELLINGTON BUILDING STRENGTHENING COSTS

Central library - $90m-$200m

Town Hall - $112m (plus $20m contingency)

St James Theatre - $34m

Wellington Museum - $31m

Municipal Office Building - $84m

Frank Kitts Park car park - $2m